Before the investment programme started our targets were: .jpg)
- By the end of the 5-year investment programme to have made 20,000 improvements.In the first year we have made 4,000 improvements even though we didn't start on site until June.
- All homes to reach the Decent Homes standard and beyond. At the start of the programme 986 out of 5,237 homes met the standard. At the start of March 2010 there are now 1,596 homes that meet the standard.
- All homes to have at least one improvement by March 2011. We are well on track to achieve this, over 3,000 out of 5,237 homes have already reacieved at least one improvement.
The improvement projects we have already started are:
Work: New upvc windows and front doors
Area: All areas.
Contractors: Allten Windows and Wrekin Windows
Started June 2009
Due to complete December 2010
.jpg)
Work: Kitchen and bathroom replacement
Area: Ardwick (New Bank Estate)
Contractor: Connaught plc
Started July 2009
Due to complete March 2011
Work: External improvements (roofing, pointing, windows, replacement of back boilers)
Area: Stanley Grove Estate
Contractor: Henry Boot Ltd
Started October 2009
Due to complete November 2010
Work: External improvements (roofing, pointing, windows, replacement of back boilers)
Area: Anson Estate
Contractor: BAAS Construction
Started October 2009
Due to complete November 2010
Work: Internal improvements (kitchens, bathrooms, rewires, boilers)
Area: All dispersed terraced properties
Contractors: Jamiesons, McCoskers and others to be appointed April 2010
Started October 2009
Due to complete December 2010
Work: High priority boiler replacements
Area: Throughout the areas
Contractor: Safe and Sound
Started December 2009
Due to complete March 2010